Construction Corner

Cleveland 3-21

 

Cleveland Street Capitol Improvement Project

 

Delta Construction finished the temporary access road to 4th Street and are making progress placing the 10” water line from 6th Street to the west on Cleveland Street.

Cleveland Street and the intersection of Cleveland & 6th St in Cottage Grove will be under construction through the end of June 2025 for a full reconstruction of the road.

6th Street will remain open throughout the duration of the project. Cleveland Street will remain open to local traffic only. Work is scheduled on Cleveland St between 7:00 AM and 5:00 PM Monday through Friday.

 

 If you have additional questions or concerns, please contact Shauna Neigh, Project Coordinator at (541)767-4153.

 

EDA Main Street Revitalization Project:

 

 For up to date information, please visit the EDA Main Street Revitalization page Here or by clicking on the ticker above.

 

Sanitary Sewer Pipe bursting Project

H & J Construction is in the final phase of the sanitary sewer line replacement project.

The pipe replacement portion of this project is complete. In the next few weeks H & J will work to return the area back to normal.

 

Douglas Street Effluent Line

 

City crews are continuing to install the 300’ of effluent line down Douglas Street. This project will extend the effluent line to Trailhead Park and then on to Bohemia Park for landscaping irrigation. Once the line has been placed the City of Cottage Grove will contract out the replacement of asphalt along North Douglas Street.